November 21, 2016 (FLINT, Mich) —Lead-tainted service lines at 460 homes have been replaced so far as part of Mayor Karen Weaver’s FAST Start initiative, with 55 homes getting new copper pipes last week.

Crews from two area companies are replacing lead and galvanized steel service lines leading from the street to the water meter in residents’ homes during this third phase of the FAST Start initiative, extending the mayor’s efforts to restore safe, clean drinking water to Flint residents. A total of 788 homes are set to get new pipes this fall.

Work crews plan to replace service pipes this week at homes on Copeman Boulevard and Begole Street between Forest Hill Avenue and Ballenger Highway; on Cumings Avenue between Pershing and Downey Street; and on Leland and Crawford streets and Alvord Avenue between South Grand Traverse Street and Fenton Road.

Mayor Weaver launched the FAST Start initiative to help resolve a number of problems created after a state-appointed emergency manager switched the City’s water source to the Flint River in 2014 without the necessary corrosion control chemicals being added. The corrosive water removed a protective coating on the inside of the pipes, causing lead to leach into the water flowing to homes and businesses in the City of Flint.

While the level of lead in Flint’s water supply has been substantially reduced since the city switched back a year ago to water delivered from Lake Huron by the Great Lakes Water Authority, residents are still being urged to drink only filtered water, and to replace their filters when needed.

So far, crews have installed new service lines at a total of 460 residences in Flint and capped the lines at three abandoned homes. Mayor Weaver’s goal is to have residents in 1,000 homes receive new pipes by the end of the year, and for thousands more to get new service lines in 2017.